The NPC’s two (2) main projects enrolled in the MRP are Capacity Addition/Construction of Power Facilities Project and Transmission Line Expansion/Addition Project. NPC’s accomplishments as of 3rd quarter of 2014 are the following:
Project | Location | Accomplishment |
Capacity Addition / Construction of Power Facilities | Batanes- 400 kW;CamSur- 175 kW;
Albay- 900 kW; Occ. Mindoro- 300 kW; W. Samar- 150 kW; S. Leyte- 300 kW; Palawan- 500 kW; Zamboanga-100 kW
Palawan- 3 MW; E. Mindanao- 3MW |
83%; The contractor completed the submission of Factory Acceptance Test (FAT) procedures and FAT results of Power Transformers and Diesel Gensets. The Gensets were already delivered and installed on-site.
26.84%; Contractor’s submission of additional Const. Drawings for NPC Approval already completed. Manufacturing/Assembly of Gensets and Power Transformers already completed. |
Transmission Line Expansion / Addition | In ckt.-kms:Palawan- 5;
Masbate- 119.42;
Occ. Mindoro- 3.81 |
Palawan: 40%. ROW cases on hearing process;
Masbate: 90%. ROW clearing completed, Lay-out and staking completed, construction on-progress;
Occ. Mindoro: 80%. ROW works completed, construction stage in progress |